中文 Book a demo

What a deployment acceptance pack contains

Case Studies · · Updated November 25, 2026 · Maintained by 962120 Anhusong

Deployments end in one of two ways: the customer signs because the evidence is there, or the customer signs because the supplier is packing up. The acceptance pack exists to make the first outcome the normal one. It is not a binder of screenshots; it is the set of records both sides would want if the deployment were audited a year later.

This note describes what goes into a pack. Client identities and commercial terms are withheld from published case notes; the structure below is the part that transfers between projects.

1. Signed scope and change log

The original scope, plus every approved change with its date and its effect on the acceptance criteria. A pack without a change log cannot explain why the delivered system differs from the document the customer approved.

2. Configuration record

A readable export of the configuration that governs behavior: dispatch weights and escalation timers, service levels, fare rules with versions and effective dates, settlement cycles, permission matrix. The record is generated from the system, not written by hand, so it cannot drift from reality.

3. Interface test results

For each interface: counterpart system, protocol, test cases, pass or fail, and the counterpart owner who witnessed the test. Interfaces tested only against a mock are marked as such, and the risk is stated in the pack rather than discovered later.

4. What does the pilot comparison prove?

Compared itemEvidenceAcceptance question
Trip completenessStep history per pilot tripDoes every trip end in a terminal state with a reason?
PunctualityWindow adherence per tripIs the pickup distribution consistent with the service level?
Fare accuracyRecompute on the pilot sampleDo recomputed amounts match the written rule?
Credential blockTest of an expired itemDoes dispatch refuse the vehicle without manual action?
SettlementOne generated statementDoes it reconcile to the trip ledger with zero unexplained difference?

5. Audit log extract

A sample of audit entries covering credential changes, manual assignments, fare adjustments and permission changes, with actor, time and reason. The point is to show that the log records what the acceptance criteria claim it records.

6. Training and handover record

Who was trained, on which role, by whom, and which supervisors were certified to train new staff. A deployment where only the supplier can train new dispatchers has not been handed over.

7. Open items register

Anything not delivered, with an owner and a date. An empty open-items register at acceptance usually means the list was not written, not that nothing remains.

Frequently asked questions

Is the pack contractual? The acceptance criteria are contractual; the pack is the evidence submitted against them. Where a criterion cannot be evidenced, acceptance is conditional and the condition is recorded.

Who signs? The person named in the scope as owning acceptance, not a project coordinator. Acceptance authority that is not written down becomes negotiable at the end of a project.

Can acceptance be staged? Yes, and it usually should be: infrastructure, master data, interfaces, pilot and cutover can each be accepted separately, which prevents one late interface from blocking acceptance of everything else.

Related: implementation describes the deployment sequence, and deployment cases show a completed acceptance pack.

Reference: SAMR Standards Public Service Platform — the Chinese national standards portal used as the reference set during acceptance.

Want to see this workflow with your own fleet data?